September 2017: Construction Schedule
Post by: Eastlands Estate, 04 Sep 2017
BUILDING
WEEK 1: Finishing phase 4A, tiling phase 4B, construct rafts for storage garages
WEEK 2: Kitchens phase 4A, tiling phase 4B, brickwork for storage garage
WEEK 3: External groundworks phase 4A, landscaping phase 4A, ceilings phase 4C, external painting complete phase 4A
WEEK 4: Complete landscaping phase 4A, start internal finishing phase 4C
CIVIL
WEEK 1: Install curbs for roads phase 4A, install electrical reticulation phase 4A
WEEK 2: Install curbs for roads phase 4A, install electrical reticulation phase 4A
WEEK 3: Install paving phase 4A, install electrical reticulation phase 5A
WEEK 4: Install electrical installation phase 5A