October 2017: Construction Schedule
Post by: Eastlands Estate, 01 Oct 2017
BUILDING
WEEK 1: S/O finishes phase 4A, late sales, external painting phase 4B, paving phase 4B
WEEK 2: Internal finishing phase 4B, level and shaping phase 4B, start rafts phase 5 and 4C
WEEK 3: Landscaping phase 4B, cabinetry phase 4B, final painting phase 4B, rafts phase 5 and 4C
WEEK 4: Handover phase 4B, internal finishing phase 4C, paving phase 4C, rafts phase 5 and 4C
CIVIL
WEEK 1: Curbs phase 4B and C
WEEK 2: Curbs phase 4B and C, paving phase 4B and C
WEEK 3: Complete curbs phase 4C, paving phase 4B and C
WEEK 4: Complete paving phase 4C