October 2016: Construction Schedule
Post by: Eastlands Estate, 01 Oct 2016
BUILDING
Week 1 Raft Construction phase 2A Wet works Phase 2A
Week 2 Raft Construction phase 2B Wet works Phase 2A
Week 3 Start tiling Phase 2A Finishing Landscaping 1 D
Week 4 Hand over Phase 1 D Finishing starts Phase 2A
CIVIL
Week 1 Phase one Civils complete Roads and curbs Phase 2 Mid October
Week 2 Start with platforms of lodge
Week 3 Complete Platforms of Lodge
Week 4 Start with raft construction of lodge