November 2015 Update
Post by: Susan Moffett, 05 Nov 2015
Eastlands is proud to announce that it has broken ground
Eastlands are extremely excited and have great pleasure in advising our clients, both existing and prospective, that construction has commenced on site. From inception we have taken great care to ensure minimal disruption to the natural fauna and flora of our indigenous environment. As a result of an environmental study we discovered African Wild Potato which is a protected medicinal plant on the site. It is with great care that we have removed and replanted each and every plant.
November Construction
Civils External
- Week 1: Setting out road
- Week 2: Construct temporary deviations
- Week 3: Clear and grub
- Week 4: Cut to fill road bed
Civils Internal
- Week 1 - Setting out of internal services
- Week 2: Excavate & install internal sewer
- Week 3: Excavate & install internal storm water
- Week 4: Start with excavation of retention ponds
Construction
- Week 1: Excavate boundary wall foundation
- Week 2: Compact, place steel & pour concrete in foundation
- Week 3: Start brickwork on boundary wall
- Week 4: Brickwork on boundary wall
Occupation date for Phase 1 - March to May 2016
Invest today and take advantage of preferential & excellent value for money offers, still available in phase 1 & 2.
Please feel free to visit us on site at the sales office, where our experienced staff are available 7 days a week from 9:00 - 17:00.
Watch this space for monthly updates!
Recent News
- Eastlands Mature Lifestyle Estate - The Road 'til Now
Post by: Eastlands Estate - Why Seniors Should Set New Year's Resolutions
Post by: Eastlands Estate - There's A Lot To Celebrate At Eastlands This Christmas!
Post by: Eastlands Estate - View All News