March 2017: Construction Schedule
Post by: Eastlands Estate, 08 Mar 2017
BUILDING
WEEK 1 Start hand over of Phase 2B
WEEK 2 Brickwork phase 3B and 3C, Internal finishing Phase 3A
WEEK 3 Brickwork complete phase 3B, Plastering phase 3B, Internal finishing Phase 3A
WEEK 4 Roofing phase 3B, Complete brickwork Phase 3C, Internal finishing Phase 3A
CIVIL
WEEK 1 Start Construction of civils phase 4 – 6, Start sewer line excavations phase 4
WEEK 2 Sewer installation Phase 5, Start stormwater installation Phase 4 - 6
WEEK 3 Start sewer installation Phase 6
WEEK 4 Complete sewer installation Phase 4 & 5