March 2016: Construction Schedule
Post by: Eastlands Estate, 01 Mar 2016
BUILDING
Week 1: Pouring concrete rafts
Week 2: Excavation rafts phase 1 B
Week 3: Excavation rafts phase 1 B
Week 4: Excavation rafts phase 1 C
CIVIL:
Week 1: Asphalt external roads
Week 2: Starting construction of internal roads
Week 3: Road levelling and paving, main entrance
Week 4: Completing internal water and sewer reticulation