June 2016: Construction Schedule
Post by: Eastlands Estate, 01 Jun 2016
BUILDING
Week 1: Final finishing phase 1A, Plaster phase1B, Brickwork phase 1C
Week 2: External works phase 1A, Ceilings phase 1 B, Starting plaster phase 1 C
Week 3: Paving phase 1A, Starting internal finishing phase 1B, Roofs phase 1C
Week 4: Completing phase 1A, Finishing phase 1B, Starting ceilings phase 1C
CIVIL
Week 1: Completing road paving phase 1 A
Week 2: Starting with bulk services, Sewer & Water
Week 3: Completing storm water dams
Week 4: Completing Bulk services Phase 1