February 2017: Construction Schedule
Post by: Eastlands Estate, 31 Jan 2017
BUILDING
WEEK 1 Constructing Rafts Phase 3, Finishing Phase 2B, External Works Phase 2B
WEEK 2 Constructing Rafts Phase 3, Brickwork Phase 3, Roofing Phase 3, External Works Phase 2B
WEEK 3 Constructing Rafts Phase 3, Brickwork Phase 3, Roofing Phase 3, Completing External Works Phase 2B
WEEK 4 Constructing Rafts Phase 3, Brickwork Phase 3, Plastering Phase 3, Handing Over Phase 2B
CIVIL
WEEK 1 Clear and Grub Phase 4-6, Impact Rolling Phase 4-6,
WEEK 2 Impact Rolling Phase 4-6
WEEK 3 Start Excavations Phase 4-6
WEEK 4 Excavations Phase 4-6