February 2016: Construction Schedule
Post by: Eastlands Estate, 01 Feb 2016
BUILDING
WEEK 1: Excavation of rafts phase 1A
WEEK 2: Excavation, placing steel in rafts phase 1 A
WEEK 3: Pouring Concrete in rafts phase 1A
WEEK 4: Starting brickwork in phase 1A
CIVIL
WEEK 1: Completion of curbs on external roads, installation of water and sewer lines internal phase 1
WEEK 2: Completion of the base layer of the external road
WEEK 3: Installation of water and sewer reticulation phase 1
WEEK 4: Tarring of the external road. Begin excavation for internal roads