December 2016: Construction Schedule
Post by: Eastlands Estate, 01 Dec 2016
BUILDING
Week 1 External work Phase 2, Finishing Phase 2A, Start internal finishing Phase 2B
Week 2 Completing external works Phase 2, Complete finishing Phase 2A, Finishing work continue Phase 2B
Week 3 Builders Break
Week 4 Builders Break
CIVILS
Week 1 Completing roads Phase 2A
Week 2 Cleaning of roads Phase 2A
Week 3 Builders Break
Week 4 Builders Break