April 2017: Construction Schedule
Post by: Eastlands Estate, 07 Apr 2017
BUILDING
WEEK 1 Internal finishing Phase 3A, Brickwork phase 3C, Plastering Phase 3B
WEEK 2 Internal finishing Phase 3A, Brickwork phase 3C, Roofing Phase 3B
WEEK 3 Internal finishing Phase 3A, Plastering Phase 3C, Roofing Phase 3C
WEEK 4 Internal finishing Phase 3B, Roofing Phase 3C, Internal finishing Phase 3B
CIVIL
WEEK 1 Completing curbs Phase 3, Paving roads Phase 3, Sewer installation Phase 4
WEEK 2 Completing paving of roads Phase 4, Sewer installation Phase 5, Start storm water installation Phase 4
WEEK 3 Construct platform Phase 4, Storm water Installation, Sewer Installation, Road beds Phase 4
WEEK 4 Storm water and Sewer installation